Rehabbing & House Flipping
Market News & Data
General Info
Real Estate Strategies
Short-Term & Vacation Rental Discussions
presented by
![](http://bpimg.biggerpockets.com/assets/forums/sponsors/hospitable-deef083b895516ce26951b0ca48cf8f170861d742d4a4cb6cf5d19396b5eaac6.png)
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
Tax, SDIRAs & Cost Segregation
presented by
![](http://bpimg.biggerpockets.com/assets/forums/sponsors/equity_trust-2bcce80d03411a9e99a3cbcf4201c034562e18a3fc6eecd3fd22ecd5350c3aa5.avif)
1031 Exchanges
presented by
![](http://bpimg.biggerpockets.com/assets/forums/sponsors/equity_1031_exchange-96bbcda3f8ad2d724c0ac759709c7e295979badd52e428240d6eaad5c8eff385.avif)
Real Estate Classifieds
Reviews & Feedback
Updated over 4 years ago on . Most recent reply
![Anthony Caiafa's profile image](https://bpimg.biggerpockets.com/no_overlay/uploads/social_user/user_avatar/1232246/1621510477-avatar-anthonyc351.jpg?twic=v1/output=image/cover=128x128&v=2)
Architecture plans timeline
how long do you usually wait for plans to be drawn up and completed?
Most Popular Reply
![Aaron McGinnis's profile image](https://bpimg.biggerpockets.com/no_overlay/uploads/social_user/user_avatar/466/1621345465-avatar-ghhaaron.jpg?twic=v1/output=image/cover=128x128&v=2)
Depends on the type of plans. Simple interior renovations with no exterior work we typically turn out in a week or two. Exterior work generally 2-3 weeks, big additions maybe 3-4 weeks, new construction about the same as big addition.
We've got two different survey companies, a cheap one and an expensive one. The cheap one takes about 3-4 weeks, the expensive one is generally around a single week. Work is comparable. Site plans, generally 1-2 weeks. (We like to get the surveyor to do the site plans for additions and new construction)