Architecture plans timeline
how long do you usually wait for plans to be drawn up and completed?
Most Popular Reply

Depends on the type of plans. Simple interior renovations with no exterior work we typically turn out in a week or two. Exterior work generally 2-3 weeks, big additions maybe 3-4 weeks, new construction about the same as big addition.
We've got two different survey companies, a cheap one and an expensive one. The cheap one takes about 3-4 weeks, the expensive one is generally around a single week. Work is comparable. Site plans, generally 1-2 weeks. (We like to get the surveyor to do the site plans for additions and new construction)