Land & New Construction
Market News & Data
General Info
Real Estate Strategies
![](http://bpimg.biggerpockets.com/assets/forums/sponsors/hospitable-deef083b895516ce26951b0ca48cf8f170861d742d4a4cb6cf5d19396b5eaac6.png)
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
![](http://bpimg.biggerpockets.com/assets/forums/sponsors/equity_trust-2bcce80d03411a9e99a3cbcf4201c034562e18a3fc6eecd3fd22ecd5350c3aa5.avif)
![](http://bpimg.biggerpockets.com/assets/forums/sponsors/equity_1031_exchange-96bbcda3f8ad2d724c0ac759709c7e295979badd52e428240d6eaad5c8eff385.avif)
Real Estate Classifieds
Reviews & Feedback
Updated about 5 years ago on . Most recent reply
![Jacob Kline's profile image](https://bpimg.biggerpockets.com/no_overlay/uploads/social_user/user_avatar/1463987/1621512546-avatar-jacobk116.jpg?twic=v1/output=image/cover=128x128&v=2)
New Construction Homes- What am I missing?
I’m a brand new investor located in St Johns County, FL. It’s difficult to find flip or rental deals here so I plan on building entry level new construction homes to build my liquidity. I know that if my #s are right, the home will sell which will allow me to build/sell 2 on the next go round, etc.
I’m wondering if I’m missing anything here in my #s so far?
So here it is:
Bought the land at a tax deed sale, plan to build a 1100sqft 3/2 home (entry level) with my own cash.
Land: $2400
Survey: $500
Quiet Title: $2500
Plans: $1000
Permitting: $3000
Impact Fees: $0 (impact credit)
Water connection fees: $5200
Septic system: $10000
Construction ($85 per sqft): $93500
Cost = $118,100
Most Popular Reply
![Greg Dickerson's profile image](https://bpimg.biggerpockets.com/no_overlay/uploads/social_user/user_avatar/1033133/1621507830-avatar-agregdickerson.jpg?twic=v1/output=image/crop=3024x3024@0x0/cover=128x128&v=2)
- Developer
- Charlottesville, VA
- 4,399
- Votes |
- 4,756
- Posts
Originally posted by @Jacob Kline:
@Greg Dickerson then I would be subject to the contractor putting a markup on materials or buying extra materials for themselves, right? This is my first project, so would like to be involved at some level to learn the process and be able to build 2 after the first sells, etc
You should be contracting the job at a turn key guaranteed price so they can’t order extra materials on your dime. You do not want to do cost plus.
The contractor can buy materials cheaper than you so the markup is a wash. If you supply materials any mistakes losses theft etc. is on you. If you let the contractor supply the materials any issues are on him.