Skip to content
×
Try PRO Free Today!
BiggerPockets Pro offers you a comprehensive suite of tools and resources
Market and Deal Finder Tools
Deal Analysis Calculators
Property Management Software
Exclusive discounts to Home Depot, RentRedi, and more
$0
7 days free
$828/yr or $69/mo when billed monthly.
$390/yr or $32.5/mo when billed annually.
7 days free. Cancel anytime.
Already a Pro Member? Sign in here

Join Over 3 Million Real Estate Investors

Create a free BiggerPockets account to comment, participate, and connect with over 3 million real estate investors.
Use your real name
By signing up, you indicate that you agree to the BiggerPockets Terms & Conditions.
The community here is like my own little personal real estate army that I can depend upon to help me through ANY problems I come across.
Land & New Construction
All Forum Categories
Followed Discussions
Followed Categories
Followed People
Followed Locations
Market News & Data
General Info
Real Estate Strategies
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
Real Estate Classifieds
Reviews & Feedback

Updated about 2 years ago on . Most recent reply

User Stats

7
Posts
2
Votes
Turner Cress
  • Rental Property Investor
  • Nashville, TN
2
Votes |
7
Posts

Delays to Expect on New Construction - Gatlinburg, Pigeon Forge

Turner Cress
  • Rental Property Investor
  • Nashville, TN
Posted

Hello,

I am hoping to get insight on what type of delays to expect in this region if I decide to invest with a builder in town, so that I can properly structure our contract and get some kind of reasonable project schedule (timeline with type of work to be performed).

Thanks for any insight.

Most Popular Reply

User Stats

100
Posts
68
Votes
Justin Beasley
  • Pigeon Forge, TN
68
Votes |
100
Posts
Justin Beasley
  • Pigeon Forge, TN
Replied

If your builder/contractor has a good track record and experience then most of your delays will come at the beginning of the project. If you buy raw land that is in critical slope and has no previous septic approval then it will take a couple of months just to get the engineered footer reports and septic approval. 

Once you break ground you will have a few weeks of delays through the life of the build....concrete, inspectors, weather, etc. A good contractor can manage anything else that arises.

Just finished one build and it was completed 5.5 months from the day we broke ground.