Skip to content
×
Pro Members Get
Full Access!
Get off the sidelines and take action in real estate investing with BiggerPockets Pro. Our comprehensive suite of tools and resources minimize mistakes, support informed decisions, and propel you to success.
Advanced networking features
Market and Deal Finder tools
Property analysis calculators
Landlord Command Center
ANNUAL Save 54%
$32.50 /mo
$390 billed annualy
MONTHLY
$69 /mo
billed monthly
7 day free trial. Cancel anytime
×
Take Your Forum Experience
to the Next Level
Create a free account and join over 3 million investors sharing
their journeys and helping each other succeed.
Use your real name
By signing up, you indicate that you agree to the BiggerPockets Terms & Conditions.
Already a member?  Login here
Contractors
All Forum Categories
Followed Discussions
Followed Categories
Followed People
Followed Locations
Market News & Data
General Info
Real Estate Strategies
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
Real Estate Classifieds
Reviews & Feedback

Updated about 9 years ago on . Most recent reply

User Stats

564
Posts
425
Votes
Luc Boiron
  • Specialist
  • Toronto, Ontario
425
Votes |
564
Posts

Experience with scheduling multiple contractor bids?

Luc Boiron
  • Specialist
  • Toronto, Ontario
Posted

I'm leading up to the closing on my first flip (details on this to come later).

I'm in the process of getting quotes for the work to be done. I've gone through the property, laid out all the work I want done. I am asking for quotes on labour only, with the contractors to pick up materials and be reimbursed for them, other than specified finishes that I will select and bring to the site.

In the past, on my long term hold properties, I have scheduled many contractors to come with 30-60min windows, and waited around all done. Some show up, some call me when other contractors are there, some are very late or early. 

This time, I have decided to have multiple contractors come at the same time. This will save me time planning and waiting around, and will hopefully lead to more competent bids. (@Marc Boiron gave me this idea, though I believe it has been said on the podcasts and forums as well).

Right now, I am planning on having 3-4 contractors scheduled each at 12pm, 2pm, and 4pm on Saturday. Some will likely not show up. I posted an ad on kijiji.ca (like craigslist but more popular here), and replied to a few ads. I have already received a number of responses from contractors, and expect I will pick the best sounding ones to come quote.

I'm hoping some people with experience in this can let me know what to expect? Are contractors ever upset to see they are scheduled at the same time as others? Should I let them know I am doing this ahead of time? Anything else I should be thinking about?

Ps: If it makes any difference, this is a condo apartment.

@Claude Boiron

Most Popular Reply

Account Closed
  • Frederick, MD
256
Votes |
654
Posts
Account Closed
  • Frederick, MD
Replied

@Luc Boiron - Pre-bid meetings like this are fantastic and we never hesitated to participate!  We were happy to know who are competition was.  Of course, it was expected that participants were vetted and pre-qualified. Plucking random folks from the internet, or the like, only invites disaster.

Construction doesn't really have trade secrets and so sharing openly was of no concern to us.

Since communication is such a large contributor to the success or failure of a project, pre-bid meetings allows everyone access to identical information at a singular time.  Properly done, minutes should be taken and distributed to all within 24 hours of the meeting.

That said, set a time (just one), stick to it and proceed.  Just send late comers away... they DQ'd themselves (barring extenuating circumstances or communication otherwise).  Equally, all questions by bidders received during the bidding period should be submitted in the form of RFI (Request for Information) and formally responded to and distributed to all bidders.  The better your plans, specifications and scope of work is, the better.

From a business standpoint, we shy away from owner supplied items. Too many variables that can cause problems (e.g., damage, warranty) and is poor business (when was the last time you brought your own beef to a restaurant for the chef to cook?).  Be specific about what you want and have the contractor provide it.  If you don't know exactly what you want, then set an allowance that you're willing to pay for that item.