Skip to content
×
PRO
Pro Members Get Full Access!
Get off the sidelines and take action in real estate investing with BiggerPockets Pro. Our comprehensive suite of tools and resources minimize mistakes, support informed decisions, and propel you to success.
Advanced networking features
Market and Deal Finder tools
Property analysis calculators
Landlord Command Center
$0
TODAY
$69.00/month when billed monthly.
$32.50/month when billed annually.
7 day free trial. Cancel anytime
Already a Pro Member? Sign in here

Join Over 3 Million Real Estate Investors

Create a free BiggerPockets account to comment, participate, and connect with over 3 million real estate investors.
Use your real name
By signing up, you indicate that you agree to the BiggerPockets Terms & Conditions.
The community here is like my own little personal real estate army that I can depend upon to help me through ANY problems I come across.
Starting Out
All Forum Categories
Followed Discussions
Followed Categories
Followed People
Followed Locations
Market News & Data
General Info
Real Estate Strategies
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
Real Estate Classifieds
Reviews & Feedback

Updated almost 9 years ago,

User Stats

40
Posts
6
Votes
Jeremy I.
  • Investor
  • Humble, TX
6
Votes |
40
Posts

Whelp, Day 1 finished, now what???

Jeremy I.
  • Investor
  • Humble, TX
Posted

BP,

I've decided to take the community through work on my first project in hopes of gaining wisdom from folks on BP.  Here is the link to my previous post:

https://www.biggerpockets.com/forums/67/topics/297...

See timeline below:

Day: Close - 2 days

Selected contractor

Day: Close

+Signed documents for closing (mobile closing)

+Received invoice from contractor and paid 1/3 of invoice for mobilization

Day: Today

+Funding not completed due to a miscommunication between lender, title and wholesaler

+Keys not provided, thus contractor was not able to start working

+Contractors diverted to another rental property to perform maintenance activity (pure dumb luck this happened at the same time)

Questions/feedback

Well, given rehab hasn't started, this day has been a big let down.  Is there anything I could have done differently?  Should I have waited until I secured the keys before officially paying for the contractor?  I did this early because I wanted to make sure I secured the contractor.  Should I consider paying the contractor for their down time today (technically I'm at fault for them not working today given I committed to the home being available today)?

Any thoughts or feedback will be greatly appreciated.