The #1 Rule Of Successful Flipping!
The #1 Rule Of Successful Flipping! - How To Flip A House From Start To Finish
Rule #1: Do NOT Listen To Me. I Survive On Sheer Dumb Luck!
What were you thinking!!
The End!
Did you really eagerly click on this post to find out 1 rule how to do flipping? Really... Come on now. .. really??
I am not sure about a one sure and proven way to do 1 and any and all flips, BUT.. I can show you how I did this one here flip son!
Instead Of Showing You How Successfully We Did This Flip,... Why Not Show You HOW We Did It Successfully?
So Deep no?
We get asked all the time if we accept credit cards or money for my awesome advice. No we don't! We take chickens, sheep, and virgins!
OK pumpkins, sit back, relax, get the popcorn, get your towels, as this is a tear jerker, pen, paper.. and throw it all out. You don't need any of it!
OK so lets begin. Guess what the first step is! GUESS I said!
You buy a house.. duhhh!!!
We Bought A House In Stafford Springs CT
First, some background. This house is in Stafford Springs CT. Small house, 1008 sq ft, 1 acre of land.
The Numbers:
- Purchase price: $41K
- Cost of Repairs: $48K (without driveway, appliances, without finding out the person that lived there used irrigation pipes and a garden hose for plumbing, and that the toilet was not hooked up to any plumbing so all the ... "ugliness".. sure, let's call it ugliness shall we.. well... if it is mine it is called "dried rose petals", fell underneath the house (no basement). Good one previous homeowner, good one!! You got us. You got us good!
- ARV: $160K-$170K
- Estimated profits: $40K
- Project Duration: 35 days
How We Bought This House:
A good flip starts with a good purchase price. Well we did kind of a bad job here. We cut the numbers a bit too close. As long nothing goes wrong (yeah I know ... what ever!). I won't go into too much detail here so I will just list the steps.
1. Seller Finds Us Online
We have the best real estate website in the world, because fairies did our SEO. Enough said! For those that do not know what SEO is.. OMGAH!!! SEO (Seriously Evil Ostriches) is very important!
Respect the SEO!!
Needless to say we get many leads so sooner than later a good lead always falls in our laps...
So one did!
2. We Do Our Due Diligence
I sent my agent this information and she (because all agents are female) started working on the comps:
This is what happens when you have solid agent seducing skillsz homie! She is awesome!
3. We Make Our Best Offer
Here is where we differ significantly from other investors. Most if not all investors will low ball the sellers. We just give our highest and best offers the first time, every time.... And don't you dare stealing this. This is our slogan!
"Our Highest And Best Offer, The First Time, Every Time!"
Awesome, I know!!
Now we have the ARV and a repair quote. After facturing in holding cost, insurance on the house selling costs, agent fees we can now make a great offer. We make this a very simple process to be honest. We just assume that al the costs involved with selling a house is 10% of the ARV. So for this case, if we sold the house for $170,000 after the repairs the selling cost would be $17,000. This includes realtor commissions.
4. Sign Contract & Close Escrow
We often get our offers accepted as we do give amazing offers, and we closed ASAP. This concludes the buying process and now we are ready to put on our flipping hats!
How We Flipped This Mouse, I mean House...
Before getting too excited, calm down buttercup! We need a plan of action! (I will assume you have a good contractor).
- Get A Solid Contact
- Divide The Scope Of Work Into several phases
- Set your deadline
- Set Up Payment agreements With Contractor For Each Phase
- Set A Starting Date IN WRITING
- Set A Finish Date IN WRITING
- Sign Lien Waiver Form BEFORE submitting payment for EVERYONE that worked on the house!
- Pay them suckers!
Phase 1: Demo/Interior Framing layout walls and rooms. [10 days]
- Demo whole house/clean up interior
- Expand walkway between living room to eating are by 3 feet (install new header)
- Frame up new laundry area, frame bedroom wall
- Frame up new patio sliding rough opening and install new sliding patio door
- Fix water damage floor in hallway
- Tile bathroom floor and walls
- Install rough electrical throughout house.
- Install rough plumbing throughout house.
- Install insulation and drywall sheetrock
- Measure windows/door. Place order for items
*Material cost of this section: Seven Thousand Dollars. $7,000,-
Phase 2: Roofing/Exterior Windows and doors. [5 days]
- Close up external side door between living room and kitchen, patch siding, patch wall
- Replace windows, replace front entry door, power wash house/deck
- Restoration of vinyl siding which includes power washing and replace any missing pieces of siding.
*Material cost of this section: Eight Thousand Nine Hundred and Sixty-four Dollars. $8,964,-
Phase 3: Interior paint/ Install kitchen cabinets and granite countertops. [5 days]
- Install bathroom vanities, toilets, sinks, tubs.
- Install hardwood flooring, Install baseboard heating, electrical, and plumbing.
*Material cost of this section: Eight Thousand Nine Hundred and Sixty-four Dollars. $8,964.-
Phase 4: Flooring and other... Stuff! [5 days]
- Final installation of lighting fixtures and electrical plates.
- Final hardware of doors and cabinets which includes knobs, hinges, plates.
- Interior trim work.
*Material cost of this section: One Thousand Two Hundred Dollars. $1,200.-
Don’t forget the payment plan. This is important to avoid issues with contractors! (see above in green text)
We are set! Let’s Flip This House
OK are we doing this or what!? Let's flip this friggin house!
… So I moved in!
So I moved in!
My office!
Day 1: Monday May 14, 2018 -The As Is Condition.
Not much was done but still an important task. Contractors and subs walked the house and got a visual. They pretty much made sure what size dumpster we needed.
Tasks:
- Ordered Dumpster
Day 2: Tuesday May 15 2018 – Subs come in to evaluate
Dumpster arrived. These Mexi's are awesome. Best contractors we ever had. I am keeping them! Got here early, started clearing the place.Filled a 30 yard dumpster in half a day!
Day 3: Wednesday May 16 2018 – Here come the issues…
Washer and Dryer were in the kitchen.. whaaaaaaa?? So that wouldn't fly. We are building a laundry/ water heater/pantry section which just has a better overall flow of the house. Problem is.. this is a 1008 square foot house. Where the heck are we going to shoe a washer and dryer! Bend over I'll show you! No no, I mean, bend over so you can see that space there under the table.. That is where we will build it!
Tasks:
- Demo Bathroom
- Framing
- Closing a room back up
Day 4: Thursday May 17 2018 – Here come the issues…
Of course something always goes wrong &$(@@^%)#! Wood rot. TOilet was not even connected! Seriously?!
Tasks:
- Finishing framing
- Put in Front Door
- Closing side door
- Cutting out back door
- Widening kitchen entry
- Putting in front door.
Adding a french door in the back.
Day 5: Friday May 18 2018 – Checking Out The Plumbing
The French door arrived. What a beauty.Time to deal with the dip in the floor. We removed the plywood flooring and
Tasks:
- Opening Floors To Access And Evaluate Plumbing
- Put in Back French Door
- Closing side door
OK SERIOUSLY?!
Irrigation pipes for plumbing nd a garden house! There goes our budget.
Purrrrrty no?
We knew from our first walk through that the floors had some issues where the well pump was. We figured it was leaking and the floor in that corner gave in.
None of the plumbing in the bathroom was connected. So the poopies just dropped to the floor under the house. And due to the vapor barrier, (a huge plastic sheet) all the little (and not so little ) poopies stayed nice moist and fresh! AWESOME!
And and AND,
They used a baseboard electrical heater under the house (I guess to keep the pipes from freezing?) and powered it with an extension cord.
How awesome is that!
Now we are waiting for a new quote from the plumber to fix it all...
This concludes the first week (5 days) of our rehab. Not bad really. Excited and lots of fun... thus far...
Day 6: Monday May 21 2018 – Ordering Windows
- Measuring Windows
- Order Windows
Day 7: Tuesday May 22 2018 – Fix Floor Joists
When we first looked at the house we noticed the floors at one spot were sagging. So let's fix it shall we?
Tasks:
- Fix Bending beams
Day 8: Wednesday May 23 2018 – Time to mow again...
Work is still halted (for the most part). We need a plumber and electrician to come in to start and finish rough work. Because plumbing was more involved than we had expected (before opening the floors), we needed to have a new quote. Our original plumber now quoted us double.
As this is in progress I decided to give the landscape tasks some attention. Tried over 15 companies to quote me on the work that needs to be done but everyone is at least 6 to 8 weeks out. That is not acceptable. I got 3 companies to give me a quote however, but they don’t do mowing. Everyone is too busy. They did quote me for weed removal, lawn treatment and mulching. They offered to plant flowers but they advised me to get the flowers myself. Even so they are still few weeks out. The quote was $560,- for it all. (We are also working on an other house with a much larger yard nd that quote was for $900,-). Nore on that house in an other blog adventure soon!
Tasks:
- Buying lawn mower
- Mow the lawn
- Buying Windows
- Got Quote for The Driveway
Day 9: Thursday May 24 2018 – Moving on
Still no plumber in sight. So we just fixed the roof...
Tasks:
- Roof Repair
- Removing popcorn ceiling
- Siding finishes of the doors
Day 10: Friday May 25 2018 – No More Popcorn Ceiling.
We gave up on scraping off the popcorn ceiling. We decided to just sheetrock over it. Shhhht
Tasks:
- Buy Sheetrock
- Install Exterior light mounts
- Install Sheetrock
Like MAGIC!
Day 11: Monday May 28 2018 – No one shows up..
Found a grill in the shed.. how convenient!! Stole a cob of corn from some farmer Joe, and chased down a raccoon and ripped a piece off of the damn critter! Happy Memorial day everyone! This is what you do when you have no family or friends in the USA! Steak is my best friend anyways!
Day 12: Tuesday May 29 2018 – Helloooo Hloooo… looooo
ECHOOOOO choooo.. ooo
Well Shnitzels.. what's going on.. no one shows up again
Day 13:Wednesday May 30 2018 – Finally, there you are…
Damn it Rocky, Don’t scare me like that…
Well it seems they had to bring mom to hospital, and that took several days. I won’t go into detail as this is personal family stuff.. so fine! We are almost half way into this flip and it is starting to warm up more now. It is time to think about curb appeal. We need to landscape. Nothing like a lush green front lawn and some color pops with pretty flowers. Laying down sod is super expensive and we have some time. Why not seed the lawn in? yes, let’s!
Meanwhile in the batcave, Mr. Rocky started to do some sheet rocking. As long as we keep on doing work, we are ok while we wait and hope for a plumber to come along!
Tasks:
- Fixing ceiling
- Yard work.
- Mowed the lawn
- Sheet rocking
Day 14: Thursday May 31 2018 – No one shows up..
Day 15: Friday June 1 2018 – Still no one.
Dude...
Day 16: Monday June 4 2018 – Washing the house
Tasks:
- Fixing ceiling
- Yard work.
- Sheet rocking
See the difference? Front face clean, side face dirty stinky and smelly, just like me!
And my job was the yard!
And finally, me as a cheerleader:
Day 17: Tuesday June 5 2018 - Back to sheetrock
We are back at it full time. Trying to do whatever work we can, so we do not fall behind due to missing plumber. Today we are doing ceiling sheetrock and other odd ends. I keep busy landscaping as well.
Tasks:
- Fixing ceiling
- Yard work.
- Sheet rocking
Day 18: Wednesday June 6 2018 – Mudding where we can
We really need to get a plumber in here. Time is starting to run out. We have had several plumbers come in but all gave us ridiculous quotes and they couldn’t start soon enough. We now have a few more to hear back from…
Tasks:
- Fixing ceiling
- Yard work.
- Sheet rocking
Day 19: Thursday June 7 2018 – FINALLY Windows are coming in!!
Good news everyone. The bay window replacement is in. And hopefully the other windows will be in tomorrow. So here is the spiffy: In our original budget we wanted to fix the od bay window as replacing it would be super costly. Sadly after we tried to fix it we encountered it was not fixable. It was rotten all the way to the core! We still didn’t want to buy a new bay window, so we decided to replace that bay window with a flat window and call it a day!
Tasks:
- Putting in Bay Window Replacement
- Fixing and replacing siding
- Odd ends
Because of the plumbing mishab, no more budget to replace the bay window. So we are just eliminating the bay window and putting a normal window in. Life stinks!
Day 20: Friday June 8 2018 – FINALLY More Windows !
The other windows came in. Today we spend the day putting windows in and starting the trim work!
Tasks:
- Putting in windows
- Trim
- Do something bout the lawn!
Still no grass damn it!!
Day 21: Friday June 9 2018 – Stare At The Grass Seed As Photons Emitted From Your Eyeballs Most Likely Will Aid It To Grow!
OK I am bored. What to do what to do...
Just pretending I am a good guy and donate some cans. I am evil I tell you. Don't let this fool you!
Tasks:
- Putting in windows
- Trim
- Stare at the grass seed as photons emitted from your eyeballs most likely will aid it grow!
Day 24: Tuesday June 12 2018 – Oh My Friggin Lawd It WORKED!!!!!!
I named them. BP Meet George (the small one all the way to the right), Winston, and Churchill, I named these 2 because they are twins. It is creepy how much alike they look, then you have Charles, Jackson and Pete, and Wilma and..
Oh yeah and some wall prep
Day 25: Wednesday June 13 2018 – Boring stuffs.. Yawns
wall prep for paint. Mudding
Tasks:
- Mudding
- Taping
- Yawning
Day 26: Thursday June 14 2018 –More Staring At The Grass For Super Fast Growth... And Plumbing
wall prep for paint. Mudding
Tasks:
- Yard staredown
- Plumbing
Day 32: Wednesday June 20 2018 –SUPERFRIENDS ASSEMBLE!!!! .... the cabinets please &... Plumbing
wall prep for paint. Mudding
Tasks:
- SUPERFRIENDS ASSEMBLE.... the cabinets please
- Plumbing
Day 34: Friday June 22 2018 –This Is What Happens When You Hire The Right People
Drive Way and Some Mexican Grill
Day 36: We Are Officially Delayed!! WHOO HOOO
If you do not get delayed or way over budget.. something is wrong. There is no way you are doing it right if you are within budget and on schedule!
OK I am Bored now.. Let's skip to the end...
So I called my magic cockroach friend. One lick over its belly and all was magically fixed!
August 16th: We Are Live On The MLS!
August 18th: OPEN HOUSE!!!
August 20th: Full Asking Price Offer Came In
$169,000.00
August 22 House Is Under Contract!! WHOO HOOO
That'll be 2 virgins, 5 chickens and a sheep (2 goats if you don't have a sheep)
Yours truly:
Monkeyboy!