Skip to content
×
PRO
Pro Members Get Full Access!
Get off the sidelines and take action in real estate investing with BiggerPockets Pro. Our comprehensive suite of tools and resources minimize mistakes, support informed decisions, and propel you to success.
Advanced networking features
Market and Deal Finder tools
Property analysis calculators
Landlord Command Center
$0
TODAY
$69.00/month when billed monthly.
$32.50/month when billed annually.
7 day free trial. Cancel anytime
Already a Pro Member? Sign in here

Join Over 3 Million Real Estate Investors

Create a free BiggerPockets account to comment, participate, and connect with over 3 million real estate investors.
Use your real name
By signing up, you indicate that you agree to the BiggerPockets Terms & Conditions.
The community here is like my own little personal real estate army that I can depend upon to help me through ANY problems I come across.
BRRRR - Buy, Rehab, Rent, Refinance, Repeat
All Forum Categories
Followed Discussions
Followed Categories
Followed People
Followed Locations
Market News & Data
General Info
Real Estate Strategies
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
Real Estate Classifieds
Reviews & Feedback

Updated over 3 years ago,

User Stats

173
Posts
129
Votes
Douglas Mcqueen
  • Rental Property Investor
  • Virginia Beach, VA (Virginia Beach)
129
Votes |
173
Posts

8 Unit BRRRR Weekly update: Week 6 the mold took hold

Douglas Mcqueen
  • Rental Property Investor
  • Virginia Beach, VA (Virginia Beach)
Posted

We are BRRRR'ing an 8 unit building in Hampton Roads region of VA, this one resides in the Ocean View Section of Norfolk. We are 6 weeks into our 8 unit rehab, for weeks 1-5 see https://www.biggerpockets.com/...

Week 6 brings the laying of the last of our landscape timbers on the exterior, this section also forms as a retaining wall to keep the parking spot we found buried. Unfortunately the weather in VA did not allow for much more outside this week.

All set to hang cabinets and lay tile in APT 77  until we realized that the mold in shared wall between the kitchen and bathroom was more than we could let slide, the dry wall however dry was barely wall and there were a multitude of bad patches from plumbing weeks of old.  Once the walls were down we soon discovered a couple of near misses from past contractors to the main water supply line running up stairs as well as a perfect shot from a finishing nail into the PVC drain.

Needless to say cabinets would have to wait and the walls came down and went back up.

Walls were up and although not ready to mount cabinets till a couple more rounds of mud can be applied we pushed ahead with laying the kitchen and bathroom tile.

Up in Apartment 11 grout is in and cleaned up and the toilet has found its new home, this one is a marked improvement form the old one we tore out.  the dark grout lines look great against the lighter tile and should show much better and require a bit less maintenance come turn time.

And finally work continues on the hallway, lots of Mud to combat 30+ years of move ins and outs, ceilings have been re-textured and painted.  Jen tackles the task of removing the grime from millions of hands off the hand rails to reveal the wood underneath that will be stained to match the stair treads once they arrive.

That's it for this weeks episode stay tuned as we continue to delve deeper in on our 8 unit BRRR