Rehabbing & House Flipping
Market News & Data
General Info
Real Estate Strategies
![](http://bpimg.biggerpockets.com/assets/forums/sponsors/hospitable-deef083b895516ce26951b0ca48cf8f170861d742d4a4cb6cf5d19396b5eaac6.png)
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
![](http://bpimg.biggerpockets.com/assets/forums/sponsors/equity_trust-2bcce80d03411a9e99a3cbcf4201c034562e18a3fc6eecd3fd22ecd5350c3aa5.avif)
![](http://bpimg.biggerpockets.com/assets/forums/sponsors/equity_1031_exchange-96bbcda3f8ad2d724c0ac759709c7e295979badd52e428240d6eaad5c8eff385.avif)
Real Estate Classifieds
Reviews & Feedback
Updated over 9 years ago on . Most recent reply
![Christy Barton's profile image](https://bpimg.biggerpockets.com/no_overlay/uploads/social_user/user_avatar/247279/1621436015-avatar-indyinvestor76.jpg?twic=v1/output=image/cover=128x128&v=2)
Using Timelines For Rehab Jobs
As someone who's had some exposure to the A&E industry, I know how important it is that projects finish on time and on or under budget (preferably the ladder). This same rule applies when trying to manage contractors on flip projects - yet I see very little in the forums/blogs about the importance of a timeline. Are others budgeting their flip projects down at the phase levels, then created subphases and tasks with est. start/completion dates? If so, how well do contractors respond to such detail and does this level of budgeting really help to keep things moving at the right pace? Are incentives used to keep your contractors on target? Are there penalties for missed deadlines?
Most Popular Reply
![David Robertson's profile image](https://bpimg.biggerpockets.com/no_overlay/uploads/social_user/user_avatar/57782/1663606773-avatar-drobertson.jpg?twic=v1/output=image/crop=991x991@0x0/cover=128x128&v=2)
- Flipper/Rehabber
- Kansas City, MO
- 750
- Votes |
- 734
- Posts
If you are going to be acting as the GC on the project and scheduling and managing subcontractors yourself, I think its a good idea to build a project schedule to help schedule contractors and manage the major project tasks.
I would typically build a rough schedule highlighting major tasks with an estimated duration/start date.
On a small project, maybe you can get away without one, but I think on anything over a month it's worth the time and effort.