Skip to content
×
Try PRO Free Today!
BiggerPockets Pro offers you a comprehensive suite of tools and resources
Market and Deal Finder Tools
Deal Analysis Calculators
Property Management Software
Exclusive discounts to Home Depot, RentRedi, and more
$0
7 days free
$828/yr or $69/mo when billed monthly.
$390/yr or $32.5/mo when billed annually.
7 days free. Cancel anytime.
Already a Pro Member? Sign in here

Join Over 3 Million Real Estate Investors

Create a free BiggerPockets account to comment, participate, and connect with over 3 million real estate investors.
Use your real name
By signing up, you indicate that you agree to the BiggerPockets Terms & Conditions.
The community here is like my own little personal real estate army that I can depend upon to help me through ANY problems I come across.
Rehabbing & House Flipping
All Forum Categories
Followed Discussions
Followed Categories
Followed People
Followed Locations
Market News & Data
General Info
Real Estate Strategies
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
Real Estate Classifieds
Reviews & Feedback

Updated over 9 years ago on . Most recent reply

User Stats

74
Posts
35
Votes
Christy Barton
  • Real Estate Agent
  • Carmel, IN
35
Votes |
74
Posts

Using Timelines For Rehab Jobs

Christy Barton
  • Real Estate Agent
  • Carmel, IN
Posted

As someone who's had some exposure to the A&E industry, I know how important it is that projects finish on time and on or under budget (preferably the ladder).  This same rule applies when trying to manage contractors on flip projects - yet I see very little in the forums/blogs about the importance of a timeline.  Are others budgeting their flip projects down at the phase levels, then created subphases and tasks with est. start/completion dates?  If so, how well do contractors respond to such detail and does this level of budgeting really help to keep things moving at the right pace?  Are incentives used to keep your contractors on target?  Are there penalties for missed deadlines?

Most Popular Reply

User Stats

734
Posts
750
Votes
David Robertson
  • Flipper/Rehabber
  • Kansas City, MO
750
Votes |
734
Posts
David Robertson
  • Flipper/Rehabber
  • Kansas City, MO
Replied

If you are going to be acting as the GC on the project and scheduling and managing subcontractors yourself, I think its a good idea to build a project schedule to help schedule contractors and manage the major project tasks.  

I would typically build a rough schedule highlighting major tasks with an estimated duration/start date.

On a small project, maybe you can get away without one, but I think on anything over a month it's worth the time and effort.