Rehabbing & House Flipping
Market News & Data
General Info
Real Estate Strategies
![](http://bpimg.biggerpockets.com/assets/forums/sponsors/hospitable-deef083b895516ce26951b0ca48cf8f170861d742d4a4cb6cf5d19396b5eaac6.png)
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
![](http://bpimg.biggerpockets.com/assets/forums/sponsors/equity_trust-2bcce80d03411a9e99a3cbcf4201c034562e18a3fc6eecd3fd22ecd5350c3aa5.avif)
![](http://bpimg.biggerpockets.com/assets/forums/sponsors/equity_1031_exchange-96bbcda3f8ad2d724c0ac759709c7e295979badd52e428240d6eaad5c8eff385.avif)
Real Estate Classifieds
Reviews & Feedback
Updated almost 10 years ago on . Most recent reply
![Matthew Herrington's profile image](https://bpimg.biggerpockets.com/no_overlay/uploads/social_user/user_avatar/225364/1645136880-avatar-fiflyer.jpg?twic=v1/output=image/crop=1331x1331@0x0/cover=128x128&v=2)
What would you pay for this Scope of Work?
Hi Guys! Anyone want to take a crack at this? Not Market specific, I am seeing $15K-$20K estimates.
Thanks, Matt
1200 sq ft., 2 outlets/ 1 switch per room.
Kitchen
-Scrape, patch, and paint
-Install new gas range
-Install new fridge
-Install Premiere Click LVT flooring
-Remove current dishwasher
-Install shelving where dishwasher was removed from
-Swap all outlets and light switches
Living Room
-Scrape, patch, and paint
-Clean carpets
-Swap all outlets and switches
Bedroom 1 (1st Floor)
-Scrape, patch, and paint
-Frame in for the installation of a door
-Install a closet system
-Swap all outlets and switches
-Remove old carpet
-Remove padding
-Remove tack strip
-Install underlayment for laminate flooring
-Install laminate flooring
-Install trim
Stairs to 2nd Floor and 2nd Floor Hallway
-Remove wall paper
-Scrape, patch, and paint
-Swap all outlets and switches
-Clean carpets on steps and in the hallway
Bathroom
-Scrape, patch, and paint
-Swap all outlets and switches
-Remove old carpet
-Remove padding
-Remove tack strip
-Install Premiere Click LVT flooring
Bedroom 2
-Scrape, patch, and paint
-Swap all outlets and switches
-Plaine down closet door so that it opens and closes properly
-Install trim
-Remove light fixture
-Install new ceiling fan
-Clean carpets
Bedroom 3
-Scrape, patch, and paint
-Swap all outlets and switches
-Remove old carpet
-Remove padding
-Remove tack strip
-Install underlayment for laminate flooring
-Install laminate flooring
-Repair or replace ceiling fan
Basement
-Scrape and paint with Killz
-Install dehumidifier
-Remove toilet in basement and cap off line where toilet was