Sample Rehab Timeline
Does anyone have a sample rehab timeline that I may look at? I will be closing Friday on a property that I am going to flip and I don't want to waste any time or money. I want to be completed all the work in 30 days. It would be great if anyone has a sample one that I can utilize.
Most Popular Reply

I can give you some average times for my average sized projects so you can at least get an idea.
roof- tear off and shingle 15 squares- 1 day
windows- remove and replace, trim outside- 8-10 per day per guy
siding- 1000 sq ft ranch- 2-3 days
bathroom gut- 2 days
my guys just sheetrocked and did first tape coat in a 10x10 bath yesterday in 2.5 hours
framing- doing a 2 story, 1000 sq ft addition now. framing should take about a week
again, your time frames could be different but it at least gives you an idea.