Question about The Time Sequence of When Things Should Be Done
Regarding to remodeling the interior of a property, what are the correct sequence of things needing to be done?
Here is what I think. Please correct me if I'm wrong:
1. Demo
2. Plumbing & electrical work
3. Bathrooms remodel
4. Paint
5. HVAC replacement
6. Kitchen
7. Flooring
I might be wrong. What's your experience on most efficient way of having things done?