Land & New Construction
Market News & Data
General Info
Real Estate Strategies
![](http://bpimg.biggerpockets.com/assets/forums/sponsors/hospitable-deef083b895516ce26951b0ca48cf8f170861d742d4a4cb6cf5d19396b5eaac6.png)
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
![](http://bpimg.biggerpockets.com/assets/forums/sponsors/equity_trust-2bcce80d03411a9e99a3cbcf4201c034562e18a3fc6eecd3fd22ecd5350c3aa5.avif)
![](http://bpimg.biggerpockets.com/assets/forums/sponsors/equity_1031_exchange-96bbcda3f8ad2d724c0ac759709c7e295979badd52e428240d6eaad5c8eff385.avif)
Real Estate Classifieds
Reviews & Feedback
Updated over 12 years ago on . Most recent reply
Questions to ask builder & realtor about spec home?
I'm meeting with a builder Tuesday morning about building two spec homes. My listing agent for another deal bought a house with four extra lots on it. She said she has another money person who wants to build on two and do I want to do the other two? I do not know this agent well. She suggested the builder.
I'm naturally cautious about these things, but want to check out what they are proposing.
What questions should I be asking during this meeting?
Here are a few details. The lots are worth about 30K each (i'm sure of this). The area is desirable with new homes being built on infill lots. These lots are flat with street frontage in the city. Almost all the new homes built in this area are 'green'. The price extremes are 175K to 350K. Most new home sell for 225-275 and are in the 1300-1600sqft range. I had previously talked with a different builder- who has a excellent reputation from multiple trusted sources and builds in the area- about building a green home with low grade but acceptable finishes. He quoted 100-105sq ft. This is lower than the finishes you would want for the best sale.
The builder I'm meeting is based in the next county over (30-40 min driving). This market is devastated compared to mine. His website shows high end homes built for a different older, more conservative buyer. No mention of green. This makes sense for that market and that my realtor would have a relationship with him, she was based in that county for many years.
My realtor mentioned a 50-50 split and that I would not pay for the lot until closing. This was in passing while we were talking other unrelated matters, so I didn't get the details. I don't like the sound of it.
What criteria would you need to go forward with this deal?
Thanks for the help. If you send me the questions, I promise I will ask every one and report back on what they say. That should be a good learning experience!
Most Popular Reply
![Brian Levredge's profile image](https://bpimg.biggerpockets.com/no_overlay/uploads/social_user/user_avatar/35439/1621368225-avatar-bclev.jpg?twic=v1/output=image/crop=1638x1638@0x205/cover=128x128&v=2)
You definitely need to factor in your soft costs on this. Those include plans, engineering, plan review, and permits among others. If you already have ready made plans, then all the better. If you don't, you'll need to either find some or have some drafted up to fit the lot accordingly. The additional fees for new construction can sometimes change the equation more than you think. For instance, Los Angeles charges a $5/sq ft school fee, which can add quite a bit to the bill, and that is in addition to the plan check and permit fees. You also need to account for the time, which can add weeks or months to your completion schedule even though you will have to invest funds up front.
With the contractor, not only do you want him to have insurance but you want to be named as an additional insured for the projects. With the subs, you may (most people don't ask for it) want to see proof of worker's comp or an affidavit from them saying they are exempt, which single employer companies usually are.
While new construction is much easier to budget for since there are usually no surprises, you may want to have the contractor include a gray clause in the contract. This is money that is set aside for unforeseen circumstances or for changes the owner might make during construction. The unused portion of money can be refundable to you if not used. As a contractor, I insisted on these clauses as even spec developers changed their mind on finishes or something else during the course of the work. They provide a nice buffer and allow you to stay within budget even if you make a couple changes. I would typically make them for 5% of the total bid.