Month 3 update on Duplex Construction w/all costs so far
Thought I'd share an update, and the costs I've hit so far on this project.
Couple of pics to start things off.
I have to be over there almost daily keeping up on stupid things and decisions the sub-contractors do not fulfill. I'm honestly really fed up with the general contractor.
As a reminder, I pay the exact invoices that are submitted to the GC. I then pay a fixed 9% fee on top of the non taxable amounts they were billed. Here are my costs so far.
Cost Summary To Date | |
Pre-Finance Appraisal | $850.00 |
Design and Engineering | $4,144.60 |
Permits | $25,438.65 |
Water/Sewer Hookups | $11,526.41 |
Builder Fee to date | $22,905.90 |
Excavation | $8,811.39 |
Toilet on-site to date | $555.41 |
Foundation | $12,582.57 |
Framing Labor | $19,853.46 |
Lumber to date | $58,047.42 |
Shower units | $2,032.53 |
Electricity to date | $210.00 |
HVAC to date (80%) | $12,583.08 |
Electrical Install | $12,848.64 |
Low voltage | $1,072.08 |
Cleaning service | $1,799.03 |
Roof + gutters | $7,245.45 |
Insulation | $10,677.41 |
Siding Labor | $7,804.80 |
Concrete (garage) | $3,605.40 |
Drywall | 21038 |
Appliances/Fixtures | 13306 |
Garage Doors | 3917 |
Cabinets | 13311 |
Doors/moulding/HW | 5976 |
Painting | 8879 |
Lights | 2339 |
Public Util | 1000 |
Window Coverings | 2000 |
Total Spend to Date | $296,360.23 |
I'm guessing I have another $50K to go.
That will put the total project (building only, I already owned the land) in the $350K range. I had budgeted $400K for the project.
Per sq foot that would be right about $105/sqft.