Land & New Construction
Market News & Data
General Info
Real Estate Strategies
Short-Term & Vacation Rental Discussions
presented by

Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
Tax, SDIRAs & Cost Segregation
presented by

1031 Exchanges
presented by

Real Estate Classifieds
Reviews & Feedback
Updated almost 8 years ago on . Most recent reply

Rock/Ledge found during site work
I'm looking at building on a site that likely has a lot of ledge/rock. From what I've seen, many contractors have a generic "there will be an extra charge" for rock/ledge removal.
Do most people push to have figured (hourly rate, per cubic yard of rock removed, etc.) added to the contract or is that wishful thinking? What is the "common" way this is addressed in most contracts? Experience with blasting vs. hammering it out, etc?
Thanks!
Ben