Skip to content
×
Try PRO Free Today!
BiggerPockets Pro offers you a comprehensive suite of tools and resources
Market and Deal Finder Tools
Deal Analysis Calculators
Property Management Software
Exclusive discounts to Home Depot, RentRedi, and more
$0
7 days free
$828/yr or $69/mo when billed monthly.
$390/yr or $32.5/mo when billed annually.
7 days free. Cancel anytime.
Already a Pro Member? Sign in here

Join Over 3 Million Real Estate Investors

Create a free BiggerPockets account to comment, participate, and connect with over 3 million real estate investors.
Use your real name
By signing up, you indicate that you agree to the BiggerPockets Terms & Conditions.
The community here is like my own little personal real estate army that I can depend upon to help me through ANY problems I come across.
Land & New Construction
All Forum Categories
Followed Discussions
Followed Categories
Followed People
Followed Locations
Market News & Data
General Info
Real Estate Strategies
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
Real Estate Classifieds
Reviews & Feedback

Updated almost 2 years ago on . Most recent reply

User Stats

26
Posts
10
Votes
Austin Ralls
10
Votes |
26
Posts

Land Development Info

Austin Ralls
Posted

I am looking for advice from anyone with experience in the land development game and insight to see how long the process generally takes for plans to be formed, approval from commissions and what others are seeing their projects timeframe being from first dirt moved to closing on the lots and getting paid out. 

Most Popular Reply

User Stats

17,764
Posts
15,296
Votes
Chris Seveney
  • Investor
  • Virginia
15,296
Votes |
17,764
Posts
Chris Seveney
  • Investor
  • Virginia
ModeratorReplied

@Austin Ralls

This is a jurisdiction by jurisdiction concern

Permitting can take anywhere from 6 months to 6 years depending on county, size and type of project.