Skip to content
×
Try PRO Free Today!
BiggerPockets Pro offers you a comprehensive suite of tools and resources
Market and Deal Finder Tools
Deal Analysis Calculators
Property Management Software
Exclusive discounts to Home Depot, RentRedi, and more
$0
7 days free
$828/yr or $69/mo when billed monthly.
$390/yr or $32.5/mo when billed annually.
7 days free. Cancel anytime.
Already a Pro Member? Sign in here

Join Over 3 Million Real Estate Investors

Create a free BiggerPockets account to comment, participate, and connect with over 3 million real estate investors.
Use your real name
By signing up, you indicate that you agree to the BiggerPockets Terms & Conditions.
The community here is like my own little personal real estate army that I can depend upon to help me through ANY problems I come across.
Contractors
All Forum Categories
Followed Discussions
Followed Categories
Followed People
Followed Locations
Market News & Data
General Info
Real Estate Strategies
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
Real Estate Classifieds
Reviews & Feedback

Updated almost 12 years ago on . Most recent reply

User Stats

2
Posts
0
Votes
Carlos Roldos
  • Dania, FL
0
Votes |
2
Posts

Contractor dispute

Carlos Roldos
  • Dania, FL
Posted

I signed a contract with a marine contractor for a dock and a seawall. The contract included 112 cu yards of fill to backfill the wall. That's what he estimated. Contract stated that any extra fill will be billed at $75.00 cu yard.
The total contract was for 29540.00 of which 5534.00 was for limerock rip rap.
Today I received an overage invoice for 7800.00 for extra 104 yards of fill.

I understand that sometimes a job can go over the quote. But is it normal to go over 20% and not inform the customer until after the fact and then demand the funds?
The funds are coming out of a 203k rehab loan. The HUD contractor is saying I should have been notified that such overrun what imminent and a change order submitted.

Any help would be appreciated.

Most Popular Reply

User Stats

399
Posts
166
Votes
Emilio Ramirez
  • Contractor
  • Denver, CO
166
Votes |
399
Posts
Emilio Ramirez
  • Contractor
  • Denver, CO
Replied

How was the scope of work defined? Did you have plans or a bid form? Was the scope of work based on a conversation between you and him? It looks like you signed his contract for the work. This is one of the reasons why I will very rarely sign a subcontractors contract. Number one, I want to write the contract so it forces me to think about every line item that I am typing. A typical clause that I include in such contracts would say something like, "any overages or extra work must be approved by the owner in writing. Any work done without prior approval in writing is at the contractors own risk."

At this point, I would go back to the contract and make sure you understand the details of it. Put it back on the contractor. Make him justify the cost. What did he figure originally? What was the reason for the overage (which his a large amount)? Without more details, it seems like bid low and change order my way into profitability.