Skip to content
×
Pro Members Get
Full Access!
Get off the sidelines and take action in real estate investing with BiggerPockets Pro. Our comprehensive suite of tools and resources minimize mistakes, support informed decisions, and propel you to success.
Advanced networking features
Market and Deal Finder tools
Property analysis calculators
Landlord Command Center
ANNUAL Save 54%
$32.50 /mo
$390 billed annualy
MONTHLY
$69 /mo
billed monthly
7 day free trial. Cancel anytime
×
Take Your Forum Experience
to the Next Level
Create a free account and join over 3 million investors sharing
their journeys and helping each other succeed.
Use your real name
By signing up, you indicate that you agree to the BiggerPockets Terms & Conditions.
Already a member?  Login here
Starting Out
All Forum Categories
Followed Discussions
Followed Categories
Followed People
Followed Locations
Market News & Data
General Info
Real Estate Strategies
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
Real Estate Classifieds
Reviews & Feedback

Updated almost 5 years ago on . Most recent reply

User Stats

34
Posts
5
Votes
Troy Kingsbury
  • Investor
  • Richmond, VA
5
Votes |
34
Posts

Schedule

Troy Kingsbury
  • Investor
  • Richmond, VA
Posted

Anyone have a schedule they use when rehabbing? What do you do 1st, 2nd, etc.? I would imagine painting and floors are last.

Most Popular Reply

User Stats

973
Posts
679
Votes
Marc Freislinger
  • Flipper
  • Phoenix, AZ
679
Votes |
973
Posts
Marc Freislinger
  • Flipper
  • Phoenix, AZ
Replied

Hello Troy,

Here is the order my crews prefer to do the work:

  1. Demo - 1 or 2 days
  2. Framing - 1 to 3 days
  3. Mechanicals (Electric, plumbing, HVAC) - 2 to 3 days
  4. Drywall - 3 to 5 days
  5. Trim and Doors - 1 to 2 days
  6. Paint - 1 to 2 days
  7. Cabinets - 1 day (order far enough in advance)
  8. Flooring - 2-4 days
  9. Counters - 1 day (order when the cabinets are installed)
  10. Fixtures (Fans, faucets, etc) - 1 to 2 days
  11. Cleaning and staging - 1 day

Some touch up paint is needed at the end, but it easier for them to spray the home when there's nothing to worry about getting paint on (no cabinets or flooring). We generally do landscaping after flooring (as the flooring guys and painters will mess up the landscape dumping their buckets), unless we need to grow grass or something that will take a few weeks, in which case the landscaping is done first thing.