Skip to content
×
Try PRO Free Today!
BiggerPockets Pro offers you a comprehensive suite of tools and resources
Market and Deal Finder Tools
Deal Analysis Calculators
Property Management Software
Exclusive discounts to Home Depot, RentRedi, and more
$0
7 days free
$828/yr or $69/mo when billed monthly.
$390/yr or $32.5/mo when billed annually.
7 days free. Cancel anytime.
Already a Pro Member? Sign in here

Join Over 3 Million Real Estate Investors

Create a free BiggerPockets account to comment, participate, and connect with over 3 million real estate investors.
Use your real name
By signing up, you indicate that you agree to the BiggerPockets Terms & Conditions.
The community here is like my own little personal real estate army that I can depend upon to help me through ANY problems I come across.
Rehabbing & House Flipping
All Forum Categories
Followed Discussions
Followed Categories
Followed People
Followed Locations
Market News & Data
General Info
Real Estate Strategies
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
Real Estate Classifieds
Reviews & Feedback

Updated almost 4 years ago on . Most recent reply

User Stats

104
Posts
37
Votes
Milind Shastri
  • Investor
  • Allen, TX
37
Votes |
104
Posts

2 months for addition permits in Dallas!

Milind Shastri
  • Investor
  • Allen, TX
Posted

Hey guys, 

We just acquired a flip project in Dallas. An architect told us that the city of Dallas is backlogged by 8 weeks for approving addition permits. I understand, we as a city, have though a lot recently but this is a waste of time! God alone knows how long we'd have to wait for an inspection.

Any one experienced with this and found a way to navigate better through this permit process? I really wish we can start work before the plan gets approved. 

Thanks,

Mil

Most Popular Reply

User Stats

4,756
Posts
4,399
Votes
Greg Dickerson#2 Land & New Construction Contributor
  • Developer
  • Charlottesville, VA
4,399
Votes |
4,756
Posts
Greg Dickerson#2 Land & New Construction Contributor
  • Developer
  • Charlottesville, VA
Replied
Originally posted by @Milind Shastri:

Hey guys, 

We just acquired a flip project in Dallas. An architect told us that the city of Dallas is backlogged by 8 weeks for approving addition permits. I understand, we as a city, have though a lot recently but this is a waste of time! God alone knows how long we'd have to wait for an inspection.

Any one experienced with this and found a way to navigate better through this permit process? I really wish we can start work before the plan gets approved. 

Thanks,

Mil

Thats pretty fast for most areas depending on what you're doing. Things are how they are right now do to Covid but the best way to get attention is to be polite, empathize with their situation as they take a lot of heat from people daily, check in regularly and take a box or two of doughnuts when you drop off the application and let them know how much you appreciate their hard work. You'll be surprised how far this can go in some permit offices.

Loading replies...