Skip to content
×
Try PRO Free Today!
BiggerPockets Pro offers you a comprehensive suite of tools and resources
Market and Deal Finder Tools
Deal Analysis Calculators
Property Management Software
Exclusive discounts to Home Depot, RentRedi, and more
$0
7 days free
$828/yr or $69/mo when billed monthly.
$390/yr or $32.5/mo when billed annually.
7 days free. Cancel anytime.
Already a Pro Member? Sign in here

Join Over 3 Million Real Estate Investors

Create a free BiggerPockets account to comment, participate, and connect with over 3 million real estate investors.
Use your real name
By signing up, you indicate that you agree to the BiggerPockets Terms & Conditions.
The community here is like my own little personal real estate army that I can depend upon to help me through ANY problems I come across.
General Real Estate Investing
All Forum Categories
Followed Discussions
Followed Categories
Followed People
Followed Locations
Market News & Data
General Info
Real Estate Strategies
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
Real Estate Classifieds
Reviews & Feedback

Updated 10 months ago on . Most recent reply

User Stats

40
Posts
19
Votes
April Birdsong
19
Votes |
40
Posts

Contractor asking for advance, for gas, etc

April Birdsong
Posted

So this is my first rental property in the middle of rehab. I paid 1/2 of negotiated labor up front and have been purchasing/paying for materials myself.  My contractor asked me for an advancement about 2 weeks ago, which I gave a small amount.  I explained that I did not mind him having a draw as long as certain work is completed, etc.  Although, I want to hold out paying for everything until it is finished.  

What have you all done in these situations. He is now starting to complain about gas money and needing to fix tire. I also have purchased some tools that I thought he would have, such as chain saw, tile cutter, etc.   He is doing a good job, but slow. And I need the work finished so that I can get it on market to rent. 

I do have a contract which states 1/2 to begin job and 1/2 on completion of the job.

I would appreciate any thoughts you have on this situation and how you have handled similar issues in the past.

Thank so much 

April

  • April Birdsong
  • Most Popular Reply

    User Stats

    11
    Posts
    9
    Votes
    Replied

    Oof sorry April, that contractor sounds...less than professional. His gas and tires are his problem, not yours. And the tools of the trade are always provided by the contractor, not his client.

    If your contract does not include some timeline for completion and/or milestones, I'd add it into future ones. These dates can be provided by the contractor, but should be something agreed to upfront. Then he can go as slow or fast as he wants based on that timeline.

    50% payment upfront is very generous with someone you don't know. Between 20-30% I believe is more typical. with other draws spelled out in the contract based on milestones and/or completed work.