Skip to content
×
PRO
Pro Members Get Full Access!
Get off the sidelines and take action in real estate investing with BiggerPockets Pro. Our comprehensive suite of tools and resources minimize mistakes, support informed decisions, and propel you to success.
Advanced networking features
Market and Deal Finder tools
Property analysis calculators
Landlord Command Center
$0
TODAY
$69.00/month when billed monthly.
$32.50/month when billed annually.
7 day free trial. Cancel anytime
Already a Pro Member? Sign in here

Join Over 3 Million Real Estate Investors

Create a free BiggerPockets account to comment, participate, and connect with over 3 million real estate investors.
Use your real name
By signing up, you indicate that you agree to the BiggerPockets Terms & Conditions.
The community here is like my own little personal real estate army that I can depend upon to help me through ANY problems I come across.
Tax, SDIRAs & Cost Segregation
All Forum Categories
Followed Discussions
Followed Categories
Followed People
Followed Locations
Market News & Data
General Info
Real Estate Strategies
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
Real Estate Classifieds
Reviews & Feedback

Updated about 4 years ago,

User Stats

7
Posts
0
Votes
Bryan B.
  • Rockwall, TX
0
Votes |
7
Posts

Problems With General Contractor

Bryan B.
  • Rockwall, TX
Posted

Hi all, I'm going to try to spell everything out the best I can without going into full specifics of things like numbers. We are in a bad situation and really don't even know where to go from here.

Earlier this year, we started a major renovation project on our home (above $100k, but let's use 100k as a base since it makes the percentages easier). In the beginning, our contractor was easy to work with, was very intimate with the job, etc. After a couple of weeks, however, he stopped being as involved, and a lot of things started going wrong. Now, as per our contract, we were to pay 30% up-front, 40% after demo, 20% at 75% mark, and 10% at the end). We had followed this to a T for the first two payments, and he requested the third payment a bit early, stating he needed it to continue work. So we gave it. At this point we had given 90% of the payment and it was a bit over half-way done.

At this point, work started to get... for lack of a better word, bad. All of a sudden things start going wrong. For example, as per our agreement and chat, we had specific things we were expecting that weren't followed through on, from materials to setup and design. This has been met with things like "I honestly forgot we agreed on this" or "Oh, I forgot to do tell them," which was then followed by asking for more money since he keeps saying his quote was based on his flawed view of what we agreed upon and it would have cost far more to do the right thing. For example, our 140' foot fence was agreed upon to be cedar, and it was done using pine (at a cost of $8k, despite originally saying it would be $6.5k, and only notifying us about the price increase after it was finished). We called this to his attention and he said he forgot we said cedar and that he would have had to charge another $5k+ for material alone. Through the entirety of working with him, he's asked for one payment after another to pay his subcontractors, so we've, based on the $100k model, paid $98k of it to him already and there's still a lot left to go on the work.

We've honestly been a bit lenient on things because we've been stuck out of our house for over 3 months during this process (we've spent over a month in hotels alone due to the massive amount of work being done and not having a kitchen for 3 months and 2 weeks now).We just want our house back.

Now, we've been called out and been asked for proof of the permit/inspection on our fence because the one he installed was not allowed by our city. Upon going to the city to get the permit, I went ahead and decided to pull all permits for work being done (things like a 2-door to 1-door garage conversion, with load-bearing wall removed, kitchen wall removal, new pantry created, turning the old pantry into a laundry room with new plumbing and a sink, extending a shower and tub into a 9' shower, and a lot of other stuff, including a lot of electrical changes like a new outlet and new light fixtures). The city notified us that no permits were ever pulled for anything. They also notified us that nobody was ever signed up as a contractor to work on our house, so now we were called out for it.

He kept saying to both us and the city that he doesn't need permits for any of the work that was done and doesn't know why they are even asking. In the end, he agreed to sign up as a contractor and pull permits. But now he's upset because of the work that has already been done and the city wanting to see behind the walls and under the new shower (and inside the garage wall where the load-bearing wall was removed to verify stability). He is pushing the idea that he trusts his workers and the work they do and so getting these permits is just a hassle for everyone and keeps saying the only reason the city cares is because "they want their money" and that it has no other purpose.

Today, he's reaching out to tell us that the city is making him rip down our fence and replace it with cedar. He says the permits he's pulling are also adding costs and that he doesn't have the money so he wants to work with us to figure out how to pay for these fixes to his work. For the fence, he wants another $5k now, again repeating that, despite our conversations talking about cedar, he thought we didn't care about the material (but wouldn't the onus be on him regardless, even if we were open to fencing type, to figure out what's allowed as per city law?). We purposely did not want pine because our last fence (before the law was changed) was pine and it had one issue after another due to weather here. He's also asking for the cost of getting permits and licensing for all of his workers, stating that he never billed us for any of this since it wasn't supposed to be needed for anything (based on what I can tell, he wasn't even planning on one for running a new power line from our breaker box to the kitchen for a double-stove). His words: "interior work doesn't need permits, only exterior work."

We are at a complete loss of what to do now. He's essentially asking for another $20k for a job we've already paid well over 100k for (and has increased costs many times along the way: for example, our stove was supposed to be included, then it was "$1100" for the wiring, then when we agreed it jumped to $1500 because he forgot it needs drywall when he finishes, and now it is jumping to $2000 since he thought he didn't need a permit for running electrical). On top of the money we've paid him, we've spent literally thousands stuck in hotels while this project has been ongoing. And now all work has been halted, leaving us with no kitchen or anything for the foreseeable future since he says he can't work on anything until we cover the costs of his permits and licensure and he doesn't have the funds to pay for any of it.

Now, with the background out of the way, here are two issues we're having.

It looks like we can't go to an attorney because it states in the contract, "In any dispute arising from or relating to this Agreement, the Parties shall first submit the dispute to mediation."

2) Regarding the licenses and permits, it specifically states: "Contractor shall at its own expense obtain all permits necessary for the work to be performed." and "All work shall be completed in a workman-like manner and in compliance with all building codes and other applicable laws." Even with this, he's stating that we are responsible for paying for this since he didn't charge us because he shouldn't need permits for anything.

We do have issues with other things as well, such as asking about making a change, him saying he would give information, and then finding out the work was already done and we were to pay x amount since it was completed, even though if we had known the cost we would have rejected it. Contract specifically says all changes must go through signed change orders but when we brought this up to him after the fact (after he had already tacked on $25k or so in charges for things we were just trying to get info on), he said he skipped them because it "is too much of a hassle to keep going back and forth with change orders."

I know this is a huge mess... and it's something I really didn't expect to end up in. We thought that by hiring a company that's verified on sites like HomeAdvisor that we were good. I never even would have fathomed a contractor not pulling permits and then trying to argue with us about how he doesn't need them since all work is "interior" and that makes permits irrelevant.

Does anyone have any clue as to where we even start with this? We've literally dumped everything we have into the project because we wanted to get it done. 3+ months without a usable home has been rough in and of itself, and now there's no end in sight. And if we have to pay attorneys up front I don't really know what to do because we quite literally are living off salads and keeping the heat off (despite it being 45 degrees inside right now) because we've had to spend so much on hotels and such while they work, plus him constantly pushing for more money and cutting off work until it's paid.

Thank you for reading this, and if there are any questions, please don't hesitate to ask.