Looking at a property in Southern WI that has an existing building plus 5 additional acres for expansion. My thoughts are to keep the existing building in place and clear an extra acre to begin with for outdoor storage (boats/ RVs/ cars, etc).
Does anyone have experience clearing land and laying down gravel? Looking for a rough ballpark estimate, the land is lightly wooded.
They go by rents. In CA, it's around 100/hr for rentals per equipment with operators. Another option is rent all equipment for a whole week then hire operators, it should take you 3-4 units with 2-3 operators (120-150/day/operator, maybe lower in your area). I would suggest a grader, road roller/compaction unit, a dozer (to extract wood/trees), and maybe a backhoe IF you need it. Have your gravel delivered, ask the guy over the phone, you'll need 3-4 inches x area, they'll figure it out.